Freeport pipline Facilities ProjectFreeport Pipeline Facilities Project -- Segment No. 4








Freeport Pipeline Facilities Project -- Segment No. 4

Project Title: Freeport Pipeline Facilities Project -- Segment No. 4
Contract No: FPL 624
Contract Amount: $11,004,010
Job Duration: 11/2007 to 01/2010
Agency: Freeport Regional Water Authority
Agency Contact: Fred Estep
Work Performed: This projects consists of the following components:
  • A 66-inch diameter, 6,830-lineal-foot pipeline
  • The pipeline will include pipe connections to Segments 2 and 3 pipeline projects.
  • The pipeline will include the construction of a parallel four-inch diameter fiber optic conduit along its length, with pull boxes.
  • A flow control facility consisting of motorized flow isolation valves and vault, energy dissipating sleeve valves, water quality sampling, flow meters, a new building, overhead hoists, and other appurtenances.
  • A surge control facility consisting of motorized flow isolation valves and vaults for the 66-inch diameter pipeline and a 72-inch diameter pipeline, flow meter for the 72-inch diameter pipeline, surge-control tank, standby generator power to the site, site security systems, site paving, water quality monitoring, circulation piping and pumps, and other operational appurtenances.
  • Air release and vacuum facilities, cathodic-protection test stations, fiber optic conduit systems, and other appurtenant pipeline features.

Slide show of this job : Images of Project