Skanska/Rados - Interstate 215 Widening| Project Title: | SANBAG Interstate 215 Widening |
| Contract No: | C09-196 |
| Contract Amount: | $154,000,000 |
| Job Duration: | 10/2009 to 10/2013 |
| Agency: | SANBAG (San Bernardino Associated Governments) |
| Agency Contact: | Doug Franco |
| Work Performed: | Work is well under way to widen the Interstate 215, a major corridor that connects residents, motorists, and visitors to California's southland. The project adds a carpool lane in both directions between I-10 and SR-210, connector ramps from I215 and SR-210, and auxiliary lanes along the corridor. The Skanska-Rados joint venture team is constructing Phase-1 and Phase-3 freeway improvements. |
| Click Here for Job Photos |